A can finish a work in 26 days and B in 13 days. They work together for 6 days and then A leaves. In how many more days will B finish the remaining work?
DiscussMedium
Loading subject content…
Loading practice questions…
A can finish a work in 26 days and B in 13 days. They work together for 6 days and then A leaves. In how many more days will B finish the remaining work?
A is twice as efficient as B. Together they finish a job in 12 days. How long would A take to do it alone?
A and B together can complete a work in 18 days. A alone can complete it in 30 days. In how many days can B alone complete the work?
A and B together can complete a work in 6 days. A alone can complete it in 9 days. In how many days can B alone complete the work?
A can do a piece of work in 21 days and B can do it in 14 days. In how many days will they finish it working together?