A can finish a work in 24 days and B in 8 days. They work together for 3 days and then A leaves. In how many more days will B finish the remaining work?
Medium
A can finish a work in 24 days and B in 8 days. They work together for 3 days and then A leaves. In how many more days will B finish the remaining work?